What is it?
A daily construction progress report, or DPR, is a dated record of planned work, work completed, quantities, supporting references and unresolved actions at a construction site. It gives the site team, builder and owner a common starting point for the next conversation.
What belongs in a construction DPR?
Start with the date, project and work area. Record the activity that was planned separately from what was completed. A message such as “work is going well” leaves the next person guessing; a named activity and location make the update easier to discuss.
Where a quantity is recorded, include its unit and a traceable reference. Link the photo or document by its file name or shared reference, rather than writing “see WhatsApp”. A progress entry records the work; it does not replace an inspection or technical approval.
- Identify the date, project and exact work area.
- Separate planned activity, completed activity, quantity and unit.
- Add a photo or document reference, blocker, next action and responsible person.
- Keep a review status so an unchecked entry is not mistaken for an agreed record.
A daily progress report example
This short example shows the level of context to capture. The quantity describes the recorded activity, not the completion percentage of the whole floor. Keep separate activities on separate rows so a pending clarification does not disappear inside a general summary.
Example dated 17 October 2026 for Sample House. Scroll horizontally to read every field.
| Work area | Planned activity | Completed activity | Quantity / unit | Photo / reference | Blocker | Next action | Responsible person |
|---|---|---|---|---|---|---|---|
| Ground floor | East wall masonry | First wall section recorded | 12 m² | PHOTO-014 | Drawing clarification pending | Confirm current drawing with engineer | Site supervisor |
Close the day with a clear next action
Agree who submits the update and who reviews it. At the end of the reporting period, check the location, quantity, unit and references together. Mark an uncertain measurement for review instead of presenting a guess as a confirmed number.
Carry each unresolved blocker into the next update with a named action owner. If yesterday’s drawing query is still open, retain its reference and current status. A daily report becomes useful when it helps someone act, rather than simply adding another file to a folder.
Use the free DPR template in Sheets or Excel
Download the blank CSV and import or open it in your spreadsheet app. It contains headers only; the example above is not included as a real record. Add one row per activity and reporting date. Keep date formats and quantity units consistent across the team.
The photo/reference column holds a reference you supply; a CSV does not upload or store images. Keep files in the project location your team uses and check that intended readers can access them. Save the working file as a spreadsheet if you add filters, formatting or extra review columns.
Connect progress to the rest of the project
A DPR is one part of the project record. Materials, drawings and owner decisions explain why an activity moved forward or stopped. Keep a weekly owner update focused on completed stages, shared photos, the next milestone and decisions due.
BuilderSetu brings residential site progress, project references, material records and owner communication into one project context. Explore the platform or request a walkthrough around your reporting process to discuss the modules and setup your team needs.
Download the blank DPR template
Free CSV with column headers only. Open it in Google Sheets or Excel and add your own site records. No email or registration is needed.
Download CSV